Answer:
Option C
Explanation:
1 child 1 day work =1192
1 adult 1 day work =196
Work done by 16 adults in 3 days =196×16×3 =12
Remaining work =(1−12) =12.
(6 adult + 4 children ) 1 day work =(696+4192) =112
112 work is done by them in 1 day
12 work is done by them (12×12) = 6 days