1)

A contractor undertakes to dig a canal 12 km long in 350 days and employes 45 men .He finds after 200 days of working that only 412 km of canal have been completed. How many extra men must be employed to finish the work in time?


A) 50

B) 45

C) 60

D) 65

E) 55

Answer:

Option E

Explanation:

4.5 km in 200 days by 45 men

now remaining 7.5 km in 150 days by 45+x men

(200×454.5) =((45+x)×1507.5)

on solving this we get x=55.

So 55 men extra are required.