1)

If 4 men or 7 boys can do a work in 29 days, then what time will 12 men and 8 boys take to do the same work?


A) 12 days

B) 6 days

C) 7 days

D) 8 days

E) 9 days

Answer:

Option C

Explanation:

4 men = 7 boys

1 man= 7/4 boys

12 men $=\frac{7}{4}\times12$ = 21 boys

(12 men + 8 boys) $=21+8$ = 29 boys

7 boys can do work in 29 days.

$\therefore$ 29 boys can do work in $\left(\frac{29\times 7}{29}\right)$ = 7 days