Answer:
Option D
Explanation:
Let name, two men $=A,B$
One boy + girl $=C$
Amount of work $A$ can do in $1$ day $=\frac{1}{5}$
Amount of work $B$ can do in $1$ day $= \frac{1}{8}$
Amount of work $A+B$ can do in $1$ day $=\frac{1}{5}+\frac{1}{8}$ $=\frac{13}{40}$
Amount of work $A+B+C$ can do $=\frac{1}{3}$
Amount of work $C$ can do in $1$ day $= \frac{1}{3}-\frac{13}{40}$ $=\frac{1}{120}$
Work $A$ can do in $1$ day: Work $B$ can do in $1$ day: Work $C$ can do in $1$ day
$=\frac{1}{5} :\frac{1}{8} :\frac{1}{120}$
From the question, one boy work $=2\times$ Girl
So, C = 2Girl + Girl $=\frac{1}{120}$
$\Leftrightarrow$ Girl's one day work $=\frac{1}{360}$
Amount to be paid to Girl $=240\times\frac{1}{120}$ = Rs.2.