Answer:
Option B
Explanation:
$(A+B)$'s 2 days work = $\left(\frac{1}{3}\times 2\right)$ $=\frac{2}{3}$.
Remaining work $=\left(1-\frac{2}{3}\right)$ $=\frac{1}{3}$.
Now, $\frac{1}{3}$ work is done by $A$ in 2 days.
Whole work will be done by $A$ in $(2\times 3)$ = 6 days.