1) A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work ? A) 5 B) 512 C) 6 D) 8 E) 9 Answer: Option CExplanation:B's 10 days' work =115×10 =23 Remaining work =(1−23) =13 Now, 118 work is done by A in 1 day. 13 work is done by A in 18×13 = 6 days.