Answer:
Option C
Explanation:
$B$'s 10 days' work $=\frac{1}{15}\times 10$ $=\frac{2}{3}$
Remaining work $=\left(1-\frac{2}{3}\right)$ $=\frac{1}{3}$
Now, $\frac{1}{18}$ work is done by $A$ in $1$ day.
$\frac{1}{3}$ work is done by $A$ in $18\times\frac{1}{3}$ = 6 days.